§ 7-500. Assigning numbers; size; when to be erected; inspections not to be made unless numbers erected.  


Latest version.
  • Street numbers will be assigned for all buildings and structures. Numbers must be erected and displayed in front of the project on a board with permanent numbers not smaller than two (2) inches. Numbers must be in place at the beginning of the job before the footing inspection is made and be continuously displayed thereafter until the job is complete and all final inspections have been made. No inspection will be made where street numbers are not in place as required above. Contractors and others shall always refer to the street number when calling the public works-development department for an inspection request or information.

(Code 1976, § 9-1003; Ord. No. 89-11, § 1(9-1001), 3-28-89)